Schedule a buld at end of iteration every other week

We have a similar need that I read in this thread that was never actually answered:

 

http://devnet.jetbrains.com/message/5452900#434152

 

Our scrum teams work in two-week iterations, with the iterations ending every other Tuesday.  We have end of iteration builds that we need to schedule in TeamCity to run every other Tuesday.  I know I can schedule a job to run every Tuesday but we need a way to schedule it to run it every OTHER Tuesday.

 

I've tried using the advanced crontab entry format, but even that doesn't seem to provide any answers.

 

Anyone have an idea on how to do this?

 

Thanks,

James

Pavel Sher JetBrains 2,359 posts since
Mar 6, 2008
Currently Being Moderated
Jan 31, 2013 11:23 PM in response to: James Barfield
Re: Schedule a buld at end of iteration every other week

What about having two schedule triggers, one for each second Tuesday and another for each fourth Tuesday of the month? For this you can specify TUE#2 and TUE#4 in Day of week field.